Project Description
- Heavy Duty Cattle Yards constructed in the North West of Western Australia
- 2000 Head Working Capacity
- 100 NB Posts & 65 NB Rails
- Built with CNC Steel Post & Rail System
- 8m Heavy Duty Concrete Loading Ramp
- Heavy Duty Calf Cradle & Race
- Hydraulic Slide Gates & 5 Way Drafting System
- Heavy Duty Cattle Crush
- Integrated Roof System
- Full 3D Working CAD Design prior to Manufacture
The project included: Design; Fabrication; Delivery to site; Structural, mechanical and installation onsite
(12 weeks Start to Finish)